20 worker take 16 days to complete a project . Find the time needed to complete this project if there are 15 workers to work on the project.

20 worker take 16 days to complete a project Find the time needed to complete this project if there are 15 workers to work on the project class=

Respuesta :

jorel1380
jorel1380 jorel1380
  • 08-06-2017
20 workers for 16 days=1 worker for 320 days
320 days/15 workers=21.3333 days for 15 workers to do the same project. ☺☺☺☺
Answer Link

Otras preguntas

A catering service offers 12 appetizers, 9 main courses, and 7 desserts. A banquet chairperson is to select 8 appetizers, 8 main courses, and 6 desserts for a b
What is the purpose of ATP molecules in plant and animal cells?
Ideas to stop prejudice and discrimination?
explain how machines make work easier if they still require that the same amount of work be done.
What is a good sentence starter for an autobiography?
What is the purpose of ATP molecules in plant and animal cells?
4x+6y+12=0 in MX+b form with explanation
Plants use nitrogen to make proteins. What is present in the soil that makes nitrogen directly available to plants? A. Air B. Water C. Sugars D. Bacteria
Compare and contrast the terms scale and scale factor.
List in the order the major blood vessels, chambers, and valves through which a drop of blood must pass in traveling from a vena cava