A flower is constructed by 44 workers in 99 days.if 121 workers are employed to do the job.how many days will it take to complete the construction.​

Respuesta :

sqdancefan
sqdancefan sqdancefan
  • 08-03-2021

9514 1404 393

Answer:

  36

Step-by-step explanation:

We assume that time is inversely proportional to the number of workers. So increasing the number of workers by a factor of 121/99 = 11/9 will decrease the number of days by a factor of 9/11.

  (9/11)(44 days) = 36 days

It will take 36 days to complete the construction with 121 workers.

Answer Link

Otras preguntas

if a rectangle has an area of 24cm2 what is the perimeter
A rectangular garden is 25ft wide. its area is 1125ft^2, what is the length of the garden?
How one culture contributed to modern science
Write 65 thousandths in standard form
Write as a repeating decimal using bar notation. Show your work. 5/11
f = ma solve for m .......
The eatery restaurant has 200 tables. On a recent evening, there were reservations for 1/10 of the tables. How many tables were reserved?
The word form for 1.070,070
Devon is trying to find the unit price on a 6 pack of energy drink on sale for $2.99. His sister says that at that price each energy drink would cost just over
Which of the following is not true regarding gases?A. When the temp of a gas decreases its volume increases if the pressure is held constant.B. Equal volumes of