It takes 10 road workers 5days to complete a road repair when working 2hours a day working at the same place how may days will it take 2 people working 5hours a day to finish it

Respuesta :

preety89 preety89
  • 09-04-2020

Answer:

The no. of days required to finish the work is = 10 days

Step-by-step explanation:

Given data

No.of workers [tex]M_{1}[/tex] = 10

No. of days [tex]D_{1}[/tex] = 5

No. of hours working [tex]H_{1}[/tex] =  2 hours

No.of workers [tex]M_{2}[/tex] = 2

No. of hours working [tex]H_{2}[/tex] =  5 hours

We know that

[tex]M_{1} D_{1} H_{1} = M_{2} D_{2} H_{2}[/tex]

10 × 5 × 2 = 2 × 5 × [tex]D_{2}[/tex]

[tex]D_{2}[/tex] = 10 Days

Therefore the no. of days required to finish the work is = 10 days

Answer Link

Otras preguntas

4 points why discrimination and racism cause problems in a multi-ethnic society. :)
Joan is H cm tall. Gill is 3 cm shorter than Joan. Write down Gill's height in terms of H please help I also continue to get these wrong and again I have a math
Is 15.07 a rational or irrational numbers
4 points why discrimination and racism cause problems in a multi-ethnic society. :)
What is 9 3/4 as a percent
A firm starts work with 110 employees for the 1st week. The number of employees rises by 6% per week. How many weeks will it take for 250 persons to be employed
Translate to an equation and solve. Let x be the unknown number. 14 is 50% of what number?
how do you factorize this expression? 8st+7su+9sv
Please help with this, and please show me the steps to getting the answers
What is the least dangerous type of volcano and why?