contestada

How much money is in the Cost Baseline if the Project Budget is $621,200 and the Management Reserve is 4.7%?
a) The cost baseline is $593,048
b) The cost baseline is $591,992
c) The cost baseline is $590,256
d) The cost baseline is $594,872

Respuesta :

Otras preguntas

List all factors of 200.​
You decide you need a new computer. The cost of the computer is $840. However, the store also offers a rent to own option with will cost $40 per week for 24 wee
please answer it step by step​
The dams built along the Tigris and Euphrates Rivers do not impact the lives of people living downstream. true or false
BRAINLIEST TO CORRECT HURRY NOW BOTH COMPLETE ANSWERS
Why was the vast Olmec trading network significant? A. Trade routes would have carried Olmec cultural influences throughout Mesoamerica. * B. The existence of a
Which set of angles are complementary in this diagram? Please help <3
Which of the following expressions is equal to m5? m · m · m · m · m m + m + m + m + m m · 5
The diameter and height of this cylinder are equal to the side length, s, of the cube in which cylinder is inscribed. What is the expression for the cylinders v
que ago aqui?4trgrerter23