A project network has the following paths. How much slack does path ABEGHI have?
Path Duration ABDFHI 41 ABEFHI 48 ABEGHI 55 ACGHI 40
a) 0 days
b) 7 days
c) 14 days
d) 17 days

Respuesta :

Otras preguntas

Eighty percent of all vehicles examined at a certain emissions inspection station pass the inspection. Assuming that successive vehicles pass or fail independen
What was the overall effect of the civil rights movement on the economic status of African Americans by 1975
What’s 36x^2 + 24xy + 4y^2? Explain the steps.
HELP please I’ll post a picture to make it easier to look at (I made it to get 20 points)!!!
Juanita, a manager at a multinational organization, is trying to carefully scan and link the firm's internal environment to its external environment. The insigh
Which statement is true? a.Problem solving can be used only to resolve simple problems. b.Problem solving can be achieved through a systematic strategy that inv
claire%20deposited%20$2,500%20into%20an%20account%20that%20accrues%20interest%20monthly.%20she%20made%20no%20additional%20deposits%20or%20withdrawals.%20after%2
Which example is a physical change? a change that produces a new element a change that breaks a bond between atoms a change that produces a new compoun
According to economic historians, modern economic growth first happened in a. 1776, when Scottish inventor James Watt perfected a powerful and efficient steam e
A certain spacecraft is x AU (Astronomical Units) from Earth. How long in seconds does it take for a signal to reach the Earth after it is transmitted from the