A can finish a work in 24 days, B in 9 days and C in 12 days. B and C together start the work but are forced to leave after 3 days.
What was the time taken by A to finish the remaining work alone?
A 5 days
B 6 days
C 10 days
D 13 days
E 16 days

Respuesta :

Otras preguntas

Do you think the American people were justified in blaming Herbert Hoover for the Great Depression?
what is the main difference between Hellenistic culture and roman culture?
Brain cells and red blood cells receive most of their energy directly from ________________.
Whichequation has a graph perpendicular to the graph of 7x = 14y -8? 1- y= - 2x-7 2-m y= - 1./2x +4 3- y = 1/2x + 1 4- y = 2x + 9
explain how changes in weather are caused by the interaction of air masses
express 396 as product of prime factors
The floor of a concert venue is 100 3/4 feet by 75 1/2 feet. what is the area of the floor?
Find the sum of the infinite geometric series. 4-4/5+4/25-4/125+...
Luis left a 15% tip on a $30.00 food bill. How much did he leave for the tip?
what distinguishes a eukaryotic cell from a prokaryotic cell is the presence of?