suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and determined that they were 3 days, 4 days, and 8 days, respectively. using pert estimation techniques, what would be the expected duration for the activity? a. 4 days b. 8 days c. 5 days d. 4.5 days

Respuesta :

Otras preguntas

How are the terms difference, sum,quotient and product alike?
if a area of a rectangle is 24,396 centimeters and if width is 38 centimeters what is length?
(-4-3)(1-(3+5))x5= how do you solve that problem ?
in what way does jefferson emphasize that the colonists complaints are against the king of england not against the british people
Identify a possible pattern. Use the pattern to write the next three numbers 152,137,122....
Why was Cyrus described as "the Great"?
describe one reason a scientist might conduct research
Defintion for filial piety
how are repetition repetition and replication alike and different
Which of the following cultural traits is addressed in both "The Youngest Doll" and the myth of "Pandora?" a. the importance of motherhood b. the role of gend