Consider the order‑requirement digraph.


Find the earliest completion time and the new critical path if task T5 is reduced to time length 7.

Give the earliest completion time as a whole number.

earliest completion time:

——————————————————-

What is the new critical path?

A. T1T4T7

B. T1T5T7

C. T2T5T7

D. T3T6T7

Consider the orderrequirement digraph Find the earliest completion time and the new critical path if task T5 is reduced to time length 7 Give the earliest compl class=

Respuesta :

Otras preguntas

why is justinian important
Fill the blanks please! Due tomorrow
Aristotle,one of the first scientists to group organisms,grouped animals according to what way?
The type of bond between atoms of potassium and chloride in a crystal of potassium chloride a. hydrogen bond b. ionic bond c. polar covalent bond d. pure co
Why does scaring someone get rid of hiccups?
please help me with this problem 3.14 = 22/7 and r = 7/4
The numerous post-war uprisings in which nationalists attempted to overthrow colonial rulers or oppressive regimes in the name of national sovereignty were know
ISSUING driver's licenses is the responsibility of which level of  government
I Need Help Please Kate has some dimes and quarters. If she has 32 coins worth a total of $5.30, how many of each type of coin does she have
Factoring trinomials word problems.